Compare two results

Relevant Risks to this Type of Project

#projects #Risks type delivery method size
19 1814 Bridge and Tunnel All All
Number Risk Frequency Prob Cost Schedule
1 different site conditions 100 0.52 5.58 0.14
2 additional right of way required 73.7 0.30 1.54 0.25
3 additional construction easements formerly labeled r-4 73.7 0.50 0.68
4 construction noise 68.4 0.41 0.25 1.00
5 relocation of utilities prior to construction 68.4 0.23 1.01 0.38
6 aashto lrfd bridge design specifications 68.4 0.36 12.50 0.35
7 additional preconstruction costs (administration and design extended overheads) due to schedule delays 68.4 0.50 -0.25 1.00
8 approval for design exceptions - conceptual design - need to submit to fhwa - have had initial discussions 63.2 0.30 1.00 1.37
9 increase cost for mitigation 63.2 0.55 0.32 3.00
10 accelerate project construction 57.9 0.46 8.19 1.15
11 utility coordination 57.9 0.48 0.70 0.75
12 change to bridge substructure design assumptions (e.g., shaft/column length, diameter) 52.6 0.60 2.11 -3.80
13 contaminated materials estimates 52.6 0.37 3.87 1.17
14 encounter significant archaeological resources 52.6 0.05 0.27 0.18
15 coordination issues 47.4 0.28 0.20 0.00
16 constructability of design 47.4 0.68 1.80 1.50
17 contractor does not comply with environmental restrictions 47.4 0.25
0.80
18 changes to design standards 47.4 0.40 1.03 0.50
19 funding delay 47.4 0.33 10.00 3.75
20 flooding, first occurance, compensible event 47.4 0.47 0.04 0.49
21 structural steel 47.4 0.48 0.00 1.10
22 matenance during construction 42.1 1.00 0.00 0.20
23 delays to finish of feis from programmatic enviromental delays 42.1 0.42
0.34
24 complete right of way acquisition for construction 42.1 0.29 0.34 5.79
25 construction delay in kg contract impacts first pontoon delivery - basin construction 42.1 0.34 0.08 0.43
26 delay in tenant relocations 42.1
1.00
27 cost premium associated with availability of labor 36.8


28 permitting 36.8 0.70 0.13 0.01
29 change in drainage design concepts 36.8 0.33 3.50 0.30
30 delays in utility relocations due to delay in field work required from utility owners 36.8 0.20 1.00
31 change orders 36.8 1.00 71.10
32 delays due to unknowns 36.8 0.73 1.00 8.00
33 additional third party agreements and/or mitigation (other than addressed separately) 36.8 0.38 5.47
34 identification of ecological species delays (falcons) 36.8 0.53
3.08
35 barge delivery is cost prohibitive due to barge draft requirements, permit restrictions, archaeological resources, source of construction materials, etc. 36.8


36 permitting and approvals for which pa has sole resp. 36.8 0.14 0.07 0.23
37 identify potential staging areas and dry dock availability 36.8


38 risk that there are issues with pontoons after they are accepted from gray's harbor. 36.8 0.32 0.45 0.77
39 design build procurement for the remaining bsb project (not ky-4) 36.8 0.56 -0.60 -7.73
40 encountering unexpected subsurface conditions 36.8 0.15
0.30
41 tunnel cross-section immersed tube tunnel (itt) vs. bored tunnel 36.8 0.25 5.00
42 additional mitigation for section 4(f) impacts 36.8 0.40

43 maintenance of traffic 36.8 0.14 0.30 0.05
44 design quality control - dbc task 36.8


45 issues gaining city of seattle and city of medina street use permit 36.8


46 safety issues 31.6 0.10 0.20
47 escalation of project costs (bids) 31.6 0.85

48 materials quality 31.6 0.60 20.00 0.30
49 bridge design put into db contract and not taken forward by the project team 31.6 0.75
-4.50
50 construction interface issues with nysdot bridge repair contractor 31.6 0.93 9.00 0.01
51 pepco utility transmission 31.6 0.10

52 staff resource limitations / compressed project schedule 31.6 0.10
0.20
53 slope stability 31.6 0.50 0.23 0.01
54 change to design assumptions (type, size, location) for montlake cut crossing bascule bridge structure 31.6 0.05 7.50
55 environmental compliance - known permit conditions/restrictions - unexpected permit conditions 31.6 0.20 1.00 0.27
56 delay in completion of phase 1 work impacts phase 2 schedule 31.6 0.75 16.88 6.00
57 market conditions: bid prices may differ from base estimate (considering uncertain contract packaging and competition)formerly labeled c-3 31.6


58 main contractor bankruptcy 31.6 0.31 0.18 2.40
59 define initial enviromental impacts 31.6
0.00 0.00
60 usace approval of ship canal crossing 26.3 0.10 0.05 0.60
61 labor shortage 26.3 0.80
0.80
62 construction schedule delay 26.3 1.00 1.00 4.34
63 weather related interruptions to construction 26.3 0.80
4.59
64 insufficient time to review and approve design leads to errors 26.3


65 discovery of unknown below grade utilities 26.3 0.35 0.90 0.66
66 additional work restrictions (e.g. noise, vibration, work hours) 26.3


67 delayed city of seattle agreements 26.3 0.27
0.80
68 wetland and aquatic habitat mitigation different than assumed 26.3


69 uncertain settlement cost of 6(f) replacement property 26.3
2.40
70 reinitiating of esa due to change in project conditions 26.3 0.13
0.43
71 additional urban design/community enhancement features 26.3
5.00
72 delays in utility agreements 26.3


73 constructability issues associated with the west approach structure 26.3


74 additional aquatic mitigation resources are required beyond those specified elsewhere 26.3


75 changed assumptions for ventilation, fire life safety and other systems in the montlake lid 26.3
11.25
76 new storm water rule - water quantity and quality issues 26.3 0.00
0.00
77 change to design assumptions for retaining walls 26.3
13.80
78 permits obtained by nysdot include stringent restrictions 26.3


79 federal highway administration approval 26.3 0.25
0.25
80 reuse and rehab existing pavement 26.3 0.60 0.38 0.00
81 opportunity associated with the maintenance facility 26.3


82 changed delivery method (design-build vs. design-bid-build) 26.3


83 mechanical failure - tbm( tunnel boring machine) breakdown 26.3


84 changes in structure and embankment 26.3 0.50
0.00
85 known hazmat mitigation 26.3


86 work restrictions 26.3


87 delayed completion of noaa right of way acquisition 26.3 0.25
1.50
88 damage to existing structures during construction (bridge, utilities, cemetery, buildings, etc.) 26.3
1.50
89 interest rates rise just before sell bonds 26.3 0.60

90 stakeholder requirements (usn, vma, vpa pilots, coast guard, us customs) 26.3


91 successful state and local permit appeal lead to a delay 26.3 0.64
2.80
92 construction delay in kg contract impacts first pontoon delivery - pontoon construction 26.3 0.65
1.95
93 coordinating with third parties 26.3


94 suicide prevention measures-netting 26.3
0.86
95 bid and award process delays 26.3 0.25
1.00
96 general uncertainty in productivity estimates / construction durations (other than captured elsewhere) 26.3 1.00

97 need for nepa(national environmental policy act) reevaluation 26.3 1.00 0.00 3.00
98 dredged material disposal - not to hars 26.3
40.00
99 delay in obtaining nycdep approvals 26.3


100 railroad involvement 26.3 0.10
0.20

Export Results