Compare two results

Relevant Risks to this Type of Project

#projects #Risks type delivery method size
20 2084 All DB All
Number Risk Frequency Prob Cost Schedule
1 additional cost for utility relocation 100 0.33 0.44 0.60
2 differing site conditions 100.00 0.35 7.67 0.50
3 delays in right of way acquisition 100.00 0.26 1.03 0.98
4 market condition 90.00 0.19 3.63
5 additional preconstruction costs (administration and design extended overheads) due to schedule delays 85.00 0.25 1.09 1.80
6 additional project costs incurred due to current accelerated base schedule 85.00 0.30 0.82 0.75
7 refinement in wetland mitigation due to change in ponds 85.00 0.05 0.07 0.03
8 construction change orders 80.00 0.67 21.84
9 weather days and holidays 70.00 0.42 11.94 2.53
10 encounter significant archaeological resources 70.00 0.20 1.07 1.87
11 additional construction easements formerly labeled r-4 70.00 0.40 3.89 2.00
12 changes to design standards 65.00 0.75 3.56
13 hazardous materials 65.00 0.16 0.04 0.04
14 opportunity to reduce wildlife mitigation costs 65.00 0.14 0.14 0.18
15 design exceptions not approved 65.00 0.40 1.87 5.03
16 change in design during construction 65.00 0.08 0.04
17 bridge design refinement 60.00 0.65 2.13 -2.30
18 additional noise reduction elements are required 60.00 -0.04 0.35 0.00
19 delays in utility relocations 55.00 0.69 0.69 3.00
20 landscaping and aesthetics cost may be reduced 55.00 -0.36 0.59
21 right of way 55.00 0.10 0.03
22 labor and material constraints due to other projects in region 55.00 0.60 0.48
23 additional refinements to floating bridge design require more wind/wave analysis (construction impact) 55.00 0.40 -0.80 0.00
24 right of way base cost adjustment 50.00


25 maintenance of traffic 50.00 0.30 0.10 0.25
26 construction noise 50.00 0.30
0.45
27 unanticipated contaminated or hazardous materials discovered during construction (other than captured separately) 50.00 0.26 0.75 0.14
28 utility coordination 50.00 0.20 0.01 1.50
29 change in environmental regulations 50.00 0.05 0.01
30 delay in environmental process 50.00 0.20
0.16
31 change in configuration of one or more interchange 50.00


32 general project delays 45.00 0.30
1.42
33 electric utility relocation 45.00 0.40 2.20 -0.75
34 additional right of way required 45.00 0.35
0.75
35 construction delay in kg contract impacts first pontoon delivery - pontoon construction 45.00 0.53
1.31
36 unsuitable soils and muck 45.00 0.39 0.39 0.75
37 design quality control - dbc task 40.00


38 environmental compliance - known permit conditions/restrictions - unexpected permit conditions 40.00 0.23 1.00 0.25
39 maintaining/damaging existing its during construction 40.00


40 federal funding making all utilities compensable 40.00 0.57 2.55 1.82
41 delay in right of way document internal approval process 40.00 0.05
0.04
42 underestimating timing and process to finalize octa/rctc cooperative agreement (orca) in order to meet rfp document preparation 40.00


43 material availability 40.00 0.10 0.05
44 erosion control 40.00 0.33 0.56
45 constructability issues associated with the west approach structure 40.00 0.50 0.43
46 delays to finish of feis from programmatic enviromental delays 40.00 0.60
0.60
47 safety issues 35.00 0.55 0.20 3.00
48 design exceptions 35.00 0.10 0.20
49 reuse pond excavation as fill 35.00 0.00 0.18
50 design schedule constraints 35.00 0.50 1.00
51 additional cost associated with anchors 35.00
0.23
52 tunnel cross-section immersed tube tunnel (itt) vs. bored tunnel 35.00 0.25 5.00
53 identify potential staging areas and dry dock availability 35.00


54 cost premium associated with availability of materials and equipment 35.00


55 delays in utility agreements 35.00 0.38
1.52
56 construction contract duration uncertainty 35.00 0.10 0.05
57 change in drainage design 35.00 0.00 85.00
58 utility relocation may not happen in time 35.00 0.48 75.00 1.52
59 utility work windows 35.00


60 additional third party agreements and/or mitigation (other than addressed separately) 35.00 0.38 5.47
61 third party utility relocation 35.00 0.35 1.00 4.00
62 risk that there are issues with pontoons after they are accepted from gray's harbor. 35.00 0.32 0.45 0.77
63 finding new sinkholes in geotech investigation (for section 1a) 35.00 0.05 0.02
64 issues gaining city of seattle and city of medina street use permit 35.00


65 delay of funding 35.00 0.30 10.00 1.50
66 condemnation takeslonger than expected (for section 1a) 35.00 0.11
0.24
67 change in tolling equipment technology 30.00 0.40 0.80
68 dredged material disposal - not to hars 30.00 0.40 20.12
69 federal highway administration approval 30.00 0.21
0.19
70 market conditions: bid prices may differ from base estimate (considering uncertain contract packaging and competition)formerly labeled c-3 30.00


71 constructability of design 30.00 0.90 -0.16 1.50
72 delays due to unknowns 30.00 0.73 1.00 8.00
73 additional mitigation for section 4(f) impacts 30.00 0.20 0.03 0.23
74 imr approval - pending fhwa approval - 30.00 0.30
0.75
75 change in critical staffing during the project 30.00 0.50 50.00 0.50
76 contaminations is a risk. soil waste on the west side, contamination on the east side 30.00 0.03 32.89 0.02
77 coordination with local agencies (for section 2a) 30.00
0.02
78 work restrictions 30.00


79 existing its fiber optic backbone 30.00
0.10
80 coordination between i-95 and the fce project 30.00 1.00 50.00 3.00
81 delays in utility agreements 25.00 0.05
0.03
82 change to lid substructure design assumptions 25.00 0.50 12.50 -3.80
83 constructability challenges near the fishing bridge 25.00 0.90 0.07
84 changed delivery method (design-build vs. design-bid-build) 25.00


85 change to design assumptions for retaining walls 25.00
13.80
86 issue in design concept is discovered during questions from bidders require additional time 25.00 1.00 25.00 3.00
87 changed assumptions for ventilation, fire life safety and other systems in the montlake lid 25.00
11.25
88 opportunity associated with the maintenance facility 25.00


89 suicide prevention measures-netting 25.00
0.86
90 design-builder innovations 25.00 0.25 0.30
91 management decisions/ priorities delay the project 25.00 0.3825 10.00 1.13125
92 additional work restrictions (e.g. noise, vibration, work hours) 25.00 1 50.00 3
93 power connections for tolling and its 25.00
1.28
94 connections between segments (for section 6) 25.00
0.18
95 water table higher than estimated 25.00
0.48
96 delay to wetland permits (or challenge to permit, such as from public opposition) 25.00 1 0.05 4.5
97 caltrans may deny the approval of encroachment permit of utility relocations-highway easement dry standpipes 25.00


98 additional aquatic mitigation resources are required beyond those specified elsewhere 25.00 0.13 0.26 0.325
99 cost premium associated with availability of labor 25.00


100 replacement of existing culverts 25.00